Service Line Timeline

How long does it take to get a new service line?

It depends upon several factors such as the scope of work, permits where required, weather conditions, etc. In cases where our existing distribution is adequate for your new service and your electrician has completed the meter enclosure installation. On average the wait should be approximately 5 working days for overhead and 15 days for underground from the time BWL receives final electrical inspection approval.